The drainage membrane and pipe along the east retaining wall. |
The east and south retaining walls are now ready for backfilling |
Slab edge formwork has been fixed along the top of the east retaining wall |
The swimming pool has been pumped out but there is still quite a bit of work to clean all the wall starter bars |
The top of the west excavation has now been battered back to prevent any further collapses |
The site is still very wet, all the pile tops are full of water |
The locations of the slab thickenings have been marked out |
A kookaburra watching everything that is going on |