Welcome

We are the owners of a 1.4 hectare block of land on the Central Coast.

The site includes areas of rainforest which have been badly overrun by non-native plants. Our project is to restore the rainforest and to build an environmentally sustainable house on the site.

This blog records the bush regeneration work we are undertaking and the progress on building the house.

Sunday, October 31, 2010

Photos from week starting 25th October

If a building is about the things that you see when it is finished then the house really started this week with the blockwork for the east retaining wall being laid.

Looking along the east retaining wall
The wall is currently about 3/4 of its final height
Walls of the equipment room
Not much change on the rest of the site.  Hopefully they will start on the swimming pool walls next

Wednesday, October 27, 2010

Photos from week starting 18th October

Progress is really starting to pick-up now that the weather is a bit more reliable.  The concrete has been poured in all the piles and footing for the east side retaining wall has been completed.

You can see the tops of the poured piles
Pile and east retaining wall footing
Footing for the equipment room
The hollow concrete blocks for the retaining walls have been delivered
A lizard sun bathing next to our driveway

Sunday, October 17, 2010

Photos from week starting 11th October

It is difficult to see from the photos how much progress was made this week as it has been all about boring the holes for the remaining piles.  The piles are socketed 1m into the rock and are between 2m and 3m deep.

Pile holes with the boring machine
More piles holes
Even more pile holes
And even more.  Who said that bored piles were boring?


Sunday, October 10, 2010

Photos from week starting 4th October

Unfortunately there were heavy showers every day this week and consequently the ground was too soft to do any work, apart from installing some pipes for the swimming pool.



The swimming pool is filling up nicely with rainwater

Add caption

Sunday, October 3, 2010

Photos from week starting 27th September

This week we achieved a major milestone with the first concrete being poured.

The base slab of the garage has been poured

Garage base with starter bars for the retaining walls

Drainage pipes have all been installed

Piles for the east retaining wall have been poured

Piles for swimming pool equipment room

The base of the swimming pool has been poured