| The drainage membrane and pipe along the east retaining wall. |
| The east and south retaining walls are now ready for backfilling |
| Slab edge formwork has been fixed along the top of the east retaining wall |
| The swimming pool has been pumped out but there is still quite a bit of work to clean all the wall starter bars |
| The top of the west excavation has now been battered back to prevent any further collapses |
| The site is still very wet, all the pile tops are full of water |
| The locations of the slab thickenings have been marked out |
| A kookaburra watching everything that is going on |
No comments:
Post a Comment